Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

June 7, 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 6/8

1 BP: 

  • No work planned at this time

2 BP:

  • Soil backfill at hoist area
  • General cleaning
  • Electrical work in penthouse
  • North and west curtain wall work
  • Louver installation at penthouse
  • Terracotta install at south and west elevations

Monday, 6/10 –Friday, 6/14:

Site Operations:

  • Deliveries ongoing by all trades through gates 1 and 3; this will result in crane operations throughout the week
  • Subcontractors to move trailers off site

Earthwork:

  • Concrete sidewalk prep, mud mat and placement at BP north along Pearl Street
  • Grading and prep for concrete pavers placement at 1BP north entry
  • Tree plantings and soils import

Façade/Roof:

1BP:

  • Complete metal panels at north vestibule and overhang
  • Roof testing

2BP:

  • Close up façade at hoist opening
    • L9 steel CW head support 
    • Roof parapet 
    • Roof infill 
    • Spray fireproofing 
    • Curtain wall
    • Metal panel 
  • Louver installation
  • Level 4 parapet/north canopy build-out
  • Rooftop rail installation
  • Curtain wall Installation to continue
  • Terracotta at south and west façade to continue
  • Level 1 framing at awnings to be completed
  • Level 1 metal panels to be installed
  • BCH signage at level 9-West ready for metal supports and terracotta

Building Interior / Utilities:

1BP:

  • Paint touch-ups
  • Final MEP controls and building controls to be connected and tested

2BP:

  • Moisture mitigation
  • Close GWB walls at shafts, stairs and penthouse
  • MEP installations on-going at all floors
  • Elevator equipment installation
  • Spray fireproofing at hoist area
  • Fire-stopping in multiple areas

Future Activities:

Site Operations:

  • Emergency egress to be altered coming out of 1BP
  • Sidewalk mock-ups in NW corner of site

Earthwork

1 BP:

  • Landscaping and hardscaping
  • Pavers and concrete placements
  • Concrete apron re-work at 1BP drop-off

2BP:

  • Excavation at rain garden and sub-grade for new temporary walkway
  • Soil grading at loading dock
  • Catenary light poles
  • Final soils and hardscaping
  • Excavation for Pearl Street town signage

Façade/Roof:

1BP:

  • North canopy glass to be installed

2BP:

  • Terracotta installation to be completed.
  • Construct loading dock entrance and door
  • Exterior doors/entrances complete
  • Exterior signage

Building Interior / Utilities:

1BP:

  • Addition lobby millwork and finishes complete
  • Final cleaning
  • Interior signage

2BP:

  • Final MEP controls and building controls to be connected and tested
  • Drywall finish and final paint
  • Specialties, millwork and finishes