Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

December 14, 2018

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 12/15

1 BP:

  • None

2 BP:

  • Materials and equipment to be hoisted to penthouse
  • Crane demobilization
  • Metal decking install at penthouse

Monday 12/17 Friday 12/21:

Site Operation:

  • Deliveries ongoing by all trades through gates 1 and 3 – this will result in crane operations throughout the week
  • Scaffold at South and West elevation at 1BP with insulation protection

Façade/Roof:

1BP:

  • 2-HR rated wall work has begun at the East wall new-existing
  • Membrane roofing and flashing
  • Brick veneer install to continue at West and North elevations

2BP:

  • Framing at penthouse to be completed
  • Air vapor barrier installation at roof
  • Complete fireproofing at exterior structural framing
  • Complete exterior metal framing at South and West elevations
  • Sheathing at South and West floors 3-8, with AVB to follow
  • Curtain wall clips, framing and punch windows install at NW and SE corners
  • Fire stopping at elevator shafts

Structural Steel:

1BP:

  • Complete

2BP:

  • Install decking to close hole at penthouse

Building Interior:

1BP:

  • Mechanical, electrical, sprinkler, and plumbing trades working on levels 2-7
  • Blocking in bathrooms 4-6
  • Drywall and taping in bathrooms levels 2-4
  • Jambs and door frames to begin between existing 1 BP and addition
  • Drywall installation at stairwells
  • Pulling cables through riser pipes

2BP:

  • Complete concrete walls at level 1
  • Select interior metal framing levels 3-8 and penthouse
  • Door frame deliveries and install
  • MEP rough installations on-going at all floors

Future Activities:

Façade/Roof:

1BP:

  • Roof installation
  • Brick veneer installation and granite base
  • Install exterior doors/frames
  • Northeast and Southeast expansion joints (new to existing) to be completed

2BP:

  • Spray fireproofing level 1
  • Roof installation
  • Exterior metal framing and sheathing
  • Punch windows delivery and install
  • AVB, metal panels and curtain wall framing and glass install
  • Rig air handling units (2) to penthouse

Building Interior / Utilities:

1BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Gypsum wall board install and taping of all floors
  • Install plumbing and toilet accessories in bathroom levels 2-6
  • Install flooring in bathrooms
  • Begin acoustic ceiling tile install

2BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Interior metal stud framing and door frame install
  • Moisture mitigation on all floors

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.