Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Look Ahead Schedule

October 19, 2018

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

The intersection of Brookline Avenue and Pearl Street will be re-paved in the next two weeks. Milling of the existing asphalt is scheduled to occur on either Thursday (10/25) or Friday (10/26), and the new paving is scheduled to be placed on either Tuesday (10/30) or Wednesday (10/31). Traffic flow along Brookline Avenue, in both directions, will be maintained during the duration of the work. Access to Pearl Street will be closed for a period of time during each step in the process. A police detail will be present to help mitigate traffic impacts.

Weekend Work – October 20:

1 BP

  • No work

2 BP

  • Spray Fireproofing
  • Material Hoist construction of remaining levels

Monday, 10/22 Friday, 10/26:

Site Operation:

  • Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week
  • Small crane on site for window installation at 1 BP
  • Soils grading around building and site utilities
  • Scaffold constructed for brick install at South and West elevation
  • Brick delivery and laydown area at 1BP

Façade/Roof:

1BP:

  • Temporary roof installation on-going
  • Roof mechanical equipment to be hoisted and set in place
  • Window installation and testing
  • Brick veneer installation
  • Parapet framing

2BP:

  • Metal stud framing delivery and install ongoing
  • Roofing installation

Structural Steel:

1BP:

  • Complete

2BP:

  • Steel penetrations and detail at penthouse

Building Interior:

1BP:

  • Mechanical, electrical, sprinkler, and plumbing trades working on levels 2-7 at 1BP
  • Concrete sealer at the mechanical penthouse
  • Interior metal framing
  • Fire stopping and expansion joist installation

2BP:

  • Spray fire proofing beams and columns
  • MEP rough installations on-going at all floors

Roadway Improvements at Pearl Street and Brookline Avenue:

  • Milling of the road surface on 10/25 or 10/26. Police detail present. Impacts to vehicular access through Pearl Street anticipated for a period of time.

Future Activities:

October - November:

Roadway Improvements at Pearl Street and Brookline Avenue:

  • Paving of the road surface on 10/30 or 10/31. Police detail present. Impacts to vehicular access through Pearl Street anticipated for a period of time.

Site Preparations:

  • Soils excavation backfill operations, soil stock piling and soils export, will be an ongoing

Building Interior / Utilities:

1BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Electrical permanent power at end of October
  • Metal stud framing
  • In-wall rough mechanical installations
  • Equipment hoisting
  • Scaffold demobilization

2BP:

  • Slab on grade to be poured at the end of October
  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Metal stud framing
  • Spray fireproofing
  • Equipment hoisting

Façade/Roof:

1BP:

  • Metal wall and parapet framing
  • Punched windows installation
  • Roof installation
  • Brick veneer installation and granite base

2BP:

  • Roof installation
  • Exterior metal framing and sheathing

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.